Weeks of 4/23/18 and 4/30/18

Project site, aerial view looking northeast, April 20, 2018

What is Happening

University Forum

  • Elevator shaftwork in passenger elevators 1 to 3
  • Sheetrocking ceiling is ongoing on levels two and three
  • Installation of roofing ballasts and pavers on levels four and five
  • Install glass fiber reinforced concrete panels at street level
  • Trenching Broadway to install telecom conduit
  • Gasketing and sealing curtain wall and storefront
  • Installing radiant heating at street-level flooring
  • Concrete pour of topping slab at street level
  • W. 129th Street between Broadway and W. 125th Street is closed through approximately June 2018
  • Work to take place on Saturdays and Sundays

Phase 2 Foundations

  • Install pressure slab at east half of site (Site 6B)
  • Import drainage stone at west half of site (Site 7)
  • Install shear walls at east half of site (Site 6B)
  • Steel erection and metal decking for west half of site (Site 7)

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
  • After-hours work for installation of electrical conduits under W. 129th Street
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts

  • No standing on W.125th Street between Broadway and W.129th Street
  • Truck loading only on the west side of Broadway from 129th to 130th streets
  • W.131st Street between Broadway and 615 W.131st Street is closed and will remain closed until the early 2019
  • W.129th Street between Broadway and W.125th Street is closed through approximately June 2018