Weeks of 9/24/18 and 10/1/18

Project site, aerial view looking northeast, September 21, 2018
What is Happening
What is Happening
The Forum
- Painting
- Punchlist, commissioning incomplete items
- Working on low voltage systems (IT, AV, security, RF)
- Work to take place on Saturdays
- Final cleaning
Phase 2 Foundations
- Install shear walls at east half of site (Site 6B)
- Steel erection and metal deck installation at east half of site (Site 6B)
- Rebar and concrete installation for west half of site (Site 7)
- Backfilling behind foundation walls
- Installation of underground plumbing
W. 132nd Street Demolition Prep
- Sidewalk repair
- Construction fence building and repair
What to Expect
What to Expect
Construction Activity
- Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
- Material deliveries to site is ongoing
Temporary Traffic and Transportation Impacts
- No standing on W. 125th Street between Broadway and W. 129th Street
- Truck loading only on the west side of Broadway from 129th to 130th streets
- W. 131st Street between Broadway and 615 W. 131st Street is closed and will remain closed until the early 2019
Please note that all activities are subject to change based on weather and other field conditions.