Weeks of 9/10/18 and 9/17/18

Project site, aerial view looking northeast, August 31, 2018

What is Happening

The Forum

  • Painting
  • Punchlist, commissioning incomplete items
  • Occupants move in the building
  • Signage installation
  • Passenger elevator 3 preparation for New York City Department of Buildings inspection
  • Working on low voltage systems
  • Work to take place on Saturdays and Sundays
  • Final cleaning
  • New York City Department of Transportation street signage installation

Phase 2 Foundations

  • Install shear walls at east half of site (Site 6B)
  • Steel erection and metal deck installation at east half of site (Site 6B)
  • Rebar and concrete installation for west half of site (Site 7)
  • Backfilling behind foundation walls

W. 132nd Street Demolition Prep

  • Sidewalk repair
  • Construction fence building and repair

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts

  • No standing on W.125th Street between Broadway and W.129th Street
  • Truck loading only on the west side of Broadway from 129th to 130th streets
  • W. 131st Street between Broadway and 615 W. 131st Street is closed and will remain closed until the early 2019