Weeks of 3/11/19 and 3/18/19

Project site, aerial view looking northeast, March 8, 2019

What is Happening

The Forum

  • Punchlist

Columbia Business School

  • Steel erection is up to level 9 and metal decking is up to level 7 at the west half of the site (Site 7)
  • Steel erection is up to level 2 at the east half of the site (Site 6B)
  • Concrete pour on the second and third floors
  • Fire egress stair deliveries
  • Network stairs installation up to the sixth floor
  • Completion of hoist installation
  • Loading dock construction
  • Installation of underground plumbing at sub-cellar 3 level
  • Vapor barrier and concrete slab on grade installation at sub-cellar 3 level
  • Spray on fire proofing of structural steel at sub-cellar 1 and sub-cellar 3 levels

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts

  • No standing on W. 125th Street between Broadway and W. 129th Street
  • Truck loading only on the west side of Broadway from 129th to 130th streets
  • W. 131st Street between Broadway and 615 W. 131st Street is closed and will remain closed until the early 2019