Weeks of 12/31/18 and 1/7/19

Project site, aerial view looking northeast, December 28, 2018

What is Happening

The Forum

  • Painting
  • Punchlist

Columbia Business School

  • Steel erection up to level 5 at the west half of the site (Site 7)
  • Level 4 decking installation at the west half of the site (Site 7)
  • Hoist pad installation at the wst half of the site (Site 7) on W. 131st Street
  • Installation of underground plumbing at sub-cellar 3 level ongoing
  • Construction of reinforced concrete floors on level 1 at east half of site (Site 6B)
  • Gate modification on 12th Avenue between 130th and 131st streets
  • Vapor barrier installation at sub-cellar 3 level

W. 132nd Street Demolition Prep

  • Installation of scaffolding
  • Asbestos abatement at buildings scheduled for future demolition

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts

  • No standing on W. 125th Street between Broadway and W. 129th Street
  • Truck loading only on the west side of Broadway from 129th to 130th streets
  • W. 131st Street between Broadway and 615 W. 131st Street is closed and will remain closed until the early 2019