Weeks of 8/20/18 and 8/27/18

Project site, aerial view looking northeast, August 10, 2018

What is Happening

The Forum

  • Painting
  • Passenger elevators 1, 2, 3 and 4 passed inspection.  PE-3 in use for construction.
  • Mechanical, electrical and plumbing commissioning
  • W. 129th Street between Broadway and W. 125th Street is closed through approximately the end of August 2018
  • Demolition and rebuilding of W. 129th Street road
  • Working on low voltage systems
  • Work to take place on Saturdays

Phase 2 Foundations

  • Finish installation of concrete pressure slab
  • Import drainage stone at east half of site (Site 6B)
  • Install shear walls at east half of site (Site 6B)
  • Steel erection on east half of site (site 6B)
  • Metal decking, rebar, and concrete for west half of site (Site 7)

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts

  • No standing on W.125th Street between Broadway and W.129th Street
  • Truck loading only on the west side of Broadway from 129th to 130th streets
  • W. 131st Street between Broadway and 615 W. 131st Street is closed and will remain closed until the early 2019
  • W. 129th Street between Broadway and W. 125th Street is closed through approximately the end of August 2018