Weeks of 8/14/17 and 8/21/17

Project site, aerial view looking northeast, August 11, 2017

What is Happening

Jerome L. Greene Science Center

  • Guard booth installation along W.130th Street

Lenfest Center for the Arts

  • Exterior base column nodes completion

University Forum

  • Electrical roughing at the below-grade level, street-level space, and second level
  • Precast installation on the east side of the second floor and third floor
  • Installing storefronts at street-level space
  • Mechanical, electrical, and plumbing roughing at the below-grade level
  • Masonry installation of auditorium walls at level two
  • Work to take place on Saturdays for the remainder of the year

Open Space: Small Square and site work on W.129th, W.130th and Broadway around Jerome L. Greene Science Center

  • Continue work in the Woodland Walk and between the Jerome L. Greene Science Center and Lenfest Center for the Arts

Phase 2 Foundations

  • Mass excavation work (westerly portion of site bounded by 12th Ave, W.130th and W.131st streets)
  • Temporary support of excavation work along W.131st Street 
  • Installation of temporary tiebacks beneath Studebaker
  • Load testing for foundation minipiles and installation of production minipiles
  • Concrete chipping, grinding of slurry wall
  • Installation of additional wells for dewatering system

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts

  • No standing on W.125th Street between Broadway and W.129th Street
  • Truck loading only on the west side of Broadway from 129th to 130th streets
  • W.131st Street between Broadway and 615 W.131st Street is closed and will remain closed until the early 2019
  • W.129th Street between Broadway and W.125th Street is closed until December 2017