Weeks of 7/23/18 and 7/30/18

Project site, aerial view looking northeast, July 20, 2018

What is Happening

University Forum

  • Painting
  • Passenger elevators 1, 2, 3 and 4 passed inspection.  PE-3 in use for construction.
  • Site work is ongoing at W. 129th Street and the intersection of W. 129th Street and W. 125th Street.
  • Mechanical, electrical and plumbing commissioning and air balancing
  • Con Edison raising manholes and vaults in preparation for restoration of roadway on W. 129th Street.
  • W. 129th Street between Broadway and W. 125th Street is closed through approximately mid-August 2018
  • Work to take place on Saturdays

Phase 2 Foundations

  • Import drainage stone at east half of site (Site 6B)
  • Install shear walls at east half of site (Site 6B)
  • Metal decking, rebar, and concrete for west half of site (Site 7)
  • Install second tower crane, east half of site (Site 6B)

What to Expect

Construction Activity

  • Regular weekday work hours: 7:00 a.m. to 6:00 p.m. Saturday and Sunday work hours: 7:00 a.m. to 5:00 p.m.
  • Material deliveries to site is ongoing

Temporary Traffic and Transportation Impacts

  • No standing on W.125th Street between Broadway and W.129th Street
  • Truck loading only on the west side of Broadway from 129th to 130th streets
  • W.131st Street between Broadway and 615 W.131st Street is closed and will remain closed until the early 2019
  • W.129th Street between Broadway and W.125th Street is closed through approximately mid-August 2018